Demand Planning in Dynamics 365 F&O: What Manufacturers Should Know

Demand planning in Dynamics 365 Finance & Operations runs through master planning, the system’s MRP engine. Master planning reads your demand signals (sales orders, sales quotations, demand forecasts and minimum stock levels), checks them against your supply (on-hand inventory and open purchase, production and transfer orders), and recommends planned orders so you can produce the right quantities when you need them.

This article was written in collaboration with Nico Papajani. We both came to Encore from the manufacturing floor, where we worked as demand planners and in manufacturing before becoming D365 Finance & Operations solution specialists. We have done planning the hard way on spreadsheets and with Dynamics 365, and we have found that a few things decide whether demand planning in F&O works: recognizing when you have outgrown informal planning, understanding the signals MRP uses, getting ownership and data right, and starting small.

This article covers what we wish every manufacturer knew before moving planning into D365 F&O: the signs you have outgrown informal planning, how MRP in Dynamics 365 actually works, what good demand planning requires, and how to get started.

For the full discussion, including a Net requirements demo, watch our recorded webinar:

Note: Even though most customers, commentators, and consultants still refer to it as Dynamics 365 Finance & Operations or D365 F&O, Microsoft now licenses it as Dynamics 365 Finance and Supply Chain Management.

What Is Demand Planning in Dynamics 365 F&O?

Demand planning in Dynamics 365 F&O runs through Master planning, the module that handles master resource planning (MRP). It looks at your demand signals, checks them against the supply you have, and recommends planned orders, so you have what you need, when you need it.

Every manufacturing company has the goal of producing goods in the right quantities and when you need them. Master planning is the umbrella over all sorts of activities that may not look like planning on the surface but contribute directly to an executable production plan, from how many production operators you need to hire for your busy season to what raw materials need to be procured, when, and in what quantities.

Demand planning is spread across many departments: procurement, the warehouse, production, and also customer service and marketing. The goal is to take that knowledge out of one person’s hands and put it into an ERP system that can operate agnostically and generate useful orders. Master planning in F&O gives you a secure set of tools that work with user input but don’t require constant maintenance if they’re configured correctly.

Signs You’ve Outgrown Spreadsheet Planning

Informal planning is planning done outside the ERP, on spreadsheets or sometimes even paper, relying on people instead of systems. These are the signs we see most often that it’s time to move planning into D365 F&O:

  • Recurring stockouts or excess inventory. Shortages even when there’s plenty on hand, or recurring excess you have to clear out with a closeout sale to free up warehouse space. Inventory you sit on for six months or a year is space and money you could be using for items that move.
  • Reactive planning. If you’re constantly expediting, changing schedules, and firefighting ahead of a promotion you knew was coming, you’re manually handling what the plan should already account for.
  • One person holds the golden key. Master planning is a complex concept, but each input is basic: when a purchase order will arrive, when a sales order will ship. If only one person knows how to interpret the plan, that’s a red flag.
  • Limited scalability. If adding a new warehouse or product line feels like a daunting task, your planning processes won’t scale with your business.

We have seen the cost of informal planning directly. One manufacturer we worked with bought goods in bulk to meet minimum order quantities. Without Master planning, the people ordering only looked at the warehouse they produced in, missed a large quantity of raw materials sitting in their bulk warehouse, ordered more, and ended up with double the inventory. MRP prevents this because it looks at the system as a whole, not a narrow sliver of inventory.

New product launches are another common example. You order just enough raw materials for an initial test run, the product succeeds, and now you need to produce more, with no safety stock and nothing in place to catch the shortage. In F&O, you can set minimum on-hand quantities, and as sales orders come in, MRP picks them up immediately and starts suggesting what to buy before you’re short.

How MRP Works in Dynamics 365 F&O

MRP in D365 F&O compares demand signals with supply and creates planned orders to cover the gap. We’ll talk about planned production orders here, but the same logic applies to items you purchase. There are some differences around capacity, schedules, and machine availability, but philosophically it’s roughly the same.

Demand signals include:

  • Sales orders. What you’ve promised to customers.
  • Sales quotations. Deals you expect to become sales orders.
  • Demand forecasts. Your expected sales by product and month, which drive long-range planning.
  • Minimum on-hand levels. Safety stock you’ve set for items such as raw materials.
  • Production orders. A production order for a finished good creates demand for the sub-assemblies on its bill of materials.

MRP then checks supply: on-hand inventory, open purchase orders and their delivery dates, open production orders, and transfer orders between warehouses. It also considers which warehouses and locations are available and your production calendar, so you don’t overload the production floor. Too much work can be almost worse than not enough.

Two setups control how this works:

  • Master plan. How planning runs across the whole system: how many days ahead and behind it looks, which demand forecast it uses (you can have several forecast models), and whether it consumes on-hand inventory before suggesting new orders. We recommend starting with a static plan because it’s the easiest to understand. (For more on static vs dynamic plans, see Master Planning in Dynamics 365 Finance & Operations.)
  • Coverage groups. How Master planning treats each item’s volatility and purchasing or production signals.

These are the levers you’ll pull and adjust. They can be warehouse-specific or plan-specific, and you can run multiple plans in the same warehouse to achieve different goals. For example, you might want Master planning to treat supply in a bulk warehouse differently from your main warehouse, with a hierarchy that decides where MRP can pull supply from. The right values always depend on your business, but the point is that MRP can be tailored to how your manufacturing process actually flows.

How Dynamics 365 Supports Better Planning Decisions

Finance & Operations supports better planning decisions by keeping every demand and supply signal in one place and connecting them. In practice, that means three things:

  1. The system becomes the source of truth. If you have a sales forecast in F&O for the next year, MRP uses it, so it needs to be accurate. You don’t have to build it inside Dynamics 365, though. Nearly every business we work with builds its forecast in Excel, and it’s fully supported to import it back into F&O. That forecast is what lets MRP see far enough ahead for materials with long lead times, since you rarely have sales orders more than a couple of months out.
  2. It connects every signal. If a purchase order is due in three months and the demand is four months out, MRP recognizes that the inbound supply covers it, so you don’t over-purchase or overproduce.
  3. It gives you history to learn from. As a demand planner, you often don’t know whether a decision was right until six months have passed. You keep asking: Did I have enough? When did we run out? Why? MRP in D365 F&O gives you a connected snapshot of inventory and demand at each point in time, which makes it much easier to learn from past outages and plan better.

In our experience, MRP starts small and keeps growing as more departments adopt it, as people get comfortable with it, and as you fine-tune the levers. That comes with time and experience in the system.

Reviewing Planned Orders: Net Requirements and Pegging

MRP recommends planned production, purchase, and transfer orders, but a planned order is only a suggestion. Someone still needs to review the dates and quantities before firming it. Never take a recommendation at face value; it always needs a human touch.

The question every planner asks is “Why is it suggesting this order for X pieces?” The Net requirements page answers it. Open it from a released product or a sales order line to see the item by site and warehouse: on-hand inventory, demand such as sales orders, firmed production orders counted as incoming supply, and the planned orders MRP suggests to cover the shortfall. Pegging shows what each line is tied to. For example, select a planned production order and pegging may show it was triggered by a specific sales order that needs three more units.

In our experience, problems are usually product-specific, and the cause is often data: the system thinks you have a thousand on hand when you actually have zero because a journal wasn’t posted. Fix the data, then click Update on the Net requirements page to recalculate that one item without running the entire batch job. Expect some trial and error while you configure MRP: run it, review the results, adjust a setting, and run it again.

What Good Demand Planning Requires

MRP is only as good as the data it receives and the people reviewing it. Four things matter most:

  1. Ownership: Decide who maintains the forecast and keeps it from going stale, who enters known changes like a busy season or product launch, who reviews and firms planned orders, and whether that person can also approve them. When someone spots an error, they’ll know what to do.
  2. Inventory accuracy: If a supplier’s purchase orders are always late and no one updates the receipt date, MRP may assume the inventory is already on hand, or the date falls outside the planning window and MRP suggests a whole new purchase order. The same goes for stock the system thinks is in a location that’s physically empty. Team discipline in updating transactions is critical.
  3. Data quality: Keep lead times and dates in line with reality. If a production order will be a week late, update it, and add a buffer: enter 10 days. The next time MRP runs, it has a better picture, and you can update the linked sales order delivery date too. You don’t need perfection. 99% accurate is usually far better than where you started.
  4. Internal governance: Outside an ERP, people have complete freedom, like starting a production order before all the materials arrive and working on the first 5% until they do. In F&O, guardrails may stop that. Everyone wants more accuracy and visibility, but people don’t often consider the growing pains that come with it. Expect some, and set a clear responsibility structure across the organization.

How to Get Started in Dynamics 365

The best way to get started with MRP in Dynamics 365 F&O is to understand your current process first, then roll out Master planning on a small scale. We recommend six steps:

  1. Map how planning happens today. Who is responsible for what, which tools you use, where your information comes from, how it’s updated, and what the escalation chain is.
  2. Map where manual decisions are made. Decisions that depend on one person need to be taken into account.
  3. Be honest about your pain points. Where are you frustrated, and where are the biggest speed bumps? MRP can exacerbate pain points if you implement it without considering everything it touches, because now your team is dealing with an unfamiliar tool on top of the existing problem. Knowing your pain points gives you a framework for configuring MRP.
  4. Review your current configuration. Lead times, warehouses, minimum and maximum quantities, and vendor setup don’t need to be perfect, but they need to be considered.
  5. Start small. Pick one product line, either a problem line or one that runs smoothly so you can see the happy path. Configure a simple static plan, run it, and review the output in Net requirements. Are you seeing the on-hand inventory, demand, and supply you expect? Once that makes sense, fine-tune the levers and expand.
  6. Don’t dump the spreadsheets right away. As a former demand planner myself, spreadsheets are close to my heart. I did demand planning on them for a long time. When I implemented Master planning, I kept my spreadsheet up to date and compared its results with MRP’s, because I knew exactly what my spreadsheet was doing. Then I slowly transitioned to using F&O exclusively. It was more work in the meantime, but it gave me the peace of mind I needed.

Spreadsheets stay useful afterward, too. They shouldn’t be the source of your data, but they can be how you analyze it. The first thing we do with many grids in Dynamics 365 is export them to Excel to make an informed decision.

MRP Is a Tool for Informed Decisions

That’s what master planning is all about: making informed decisions. MRP in Dynamics 365 is a powerful tool, and one of the most interconnected parts of the system, but its recommendations still deserve the same consideration as every other decision you make.

If you’d like to talk about your current planning processes or how you’re using D365 F&O today, contact Encore.

As a Dynamics 365 Finance & Operations Partner, we are here to help you get the most from your Dynamics 365 solutions.

FAQs

Demand planning in Dynamics 365 F&O uses Master planning, the system’s MRP engine, to compare demand signals such as sales orders, quotations, forecasts, and minimum stock levels with available supply, then recommend planned production, purchase, and transfer orders.

MRP uses sales orders, sales quotations, demand forecasts, minimum on-hand levels, and production orders. It then checks supply: on-hand inventory and open purchase, production, and transfer orders.

Not right away. Run your spreadsheet alongside MRP during the transition to check the results. Afterward, Dynamics 365 Finance & Operations should be the source of truth, but spreadsheets remain useful for analysis.

Open the Net requirements page for the item and use pegging, which shows the transaction, such as a specific sales order, that triggered each planned order.

Inventory Management vs. Warehouse Management in D365 F&O: What to Know Before You Decide

Discover how to choose the right inventory and warehouse management approach in Dynamics 365 F&O to support current operations and future business growth.

November 17 9:00 am – 9:45 am PST

Register here

Inventory vs. Warehouse Management in F&O

November 17 9:00 am – 9:45 am PST

Register

Suggested Articles: